- Home
- Riverside Place FAQs
Updates on Riverside Place
We want to make sure you have an easy to access place for the latest updates and commonly asked questions about the situation at Riverside Place.
This page will be regularly updated, in line with any communications we send to you directly.
Last update: October 2026
If you have any other questions, please share these with us using the email address below:
When can we return to our homes?
As we shared with you at the end of September, a further delay to the timeframes has meant we now expect customers to be able to return to their homes in August 2027.
Previously, we had intended for customers to return to their homes in January 2027 but as our contractor continued to complete the external fire remediation phase at Riverside Place, they identified further issues which needed to be rectified to ensure we met all of the building requirements for completion.
Where are we up to with progress on site?
This latest delay relates to work on the piers (front of the blocks river-facing), where it became apparent that the existing piers were not tied into the building as they should have been. Our contractor Durkan has therefore moved forward with a proposed solution.
We expect Durkan to now have completed the external works by Friday 4th December 2026, with scaffold removal by the end of December 2026.
This will allow our current contractor to leave site by early January 2027, ready for the internal works to be carried out.
While we originally planned to have the internal works progressing at the same time as the external works, this has not been possible. We have tendered for a new contractor to do these works, following Durkan leaving site. This new contractor will be starting on site in February 2027.
We intend to continue to provide monthly progress updates to all customers about work completed on site.
What about my request for a buy back?
As we shared with customers at the end of September, we have continued to hold regular and in-depth discussions with our Executive team about the situation at Riverside Place, and a decision has been made to offer each customer a buy back, in light of the continued circumstances.
Over the coming weeks and months, we will be sharing further information and updates with customers about how the process will work, expectations and timeframes to expect, and working individually with customers to understand their specific needs and circumstances.
This buy back offer does not impact us supporting you to return to your home at Riverside Place, if that is what you would still prefer, nor will it create any additional delays.
What about council tax payments and compensation?
We want to reassure customers that we will continue to make council tax payments and provide compensation throughout the duration of the further delays.
The next round of council tax payments and compensation amounts are being processed and paid currently.
With the extension to the timeline needed for the works, we have made these council tax payments to cover until the end of the 2026/27 financial year, so up to March 2027.
What about my current alternative accommodation?
Likewise, we will continue to support customers with their alternative accommodation until your home at Riverside Place is ready to return to.
Where needed, we will be in touch with customers individually to extend their temporary tenancies or resolve any issues which arise.
Previous monthly progress updates
August 2026
North – West - East elevations:
• Additional pier steel - 100% complete
• Vertical railing - 100% complete
• Insulation - 100% complete
• Fire Breaks - 100% complete
• Balcony bracketry (north side) – 100% complete
• Boarding - 100% complete up to piers. Blockwork to be completed to enable remaining boarding
• Blockwork - 20% complete
• Render - 5% complete
South elevation (river facing elevation):
• Additional pier steel - 100% complete
• Blockwork - 20% complete
• Cavity barriers - 55% complete
• Vertical rails - 70% complete
• Insulation - 20% complete
Small Block (Shared Ownership homes)
June 2026
Progress made this month:
Installation of vertical railing – 80% complete
Installation of new insulation – 75% complete
Installation of fire breaks – 75% complete
Installation of boarding – 50% complete
Work started on Equitone cladding
Large Block (Social rented homes)
Progress made this month:
Installation of vertical railing – 70% complete
Installation of new insulation – 45% complete
Installation of fire barriers – 70% complete
Installation of boarding – 20% complete
Work started on Equitone cladding
May 2026
Small Block (Shared Ownership homes)
Progress made this month:
- Installation of C channels (structural beams) – 98% complete
- Installation of new cladding support system – 98% complete
- Installation of vertical railing – 65% complete
- Installation of new insulation – 65% complete
- Installation of new fire cavity barriers – 75% complete
- Installation of render carrier board – 20% complete
Large Block (Social rented homes)
Progress made this month:
- Installation of C channels (structural beams) – 98% complete
- Installation of new cladding support system – 98% complete
- Installation of vertical railing – 70% complete
- Installation of new insulation – 40% complete
- Installation of new fire cavity barriers – 70% complete
- Installation of render carrier board – 20% complete
April 2026
Small Block (Shared Ownership homes)
Current progress this month:
- Installation of the new cladding support system – 95% complete
- Installation of vertical railing – 40% complete
- Installation of new insulation – 50% complete
- Installation of new fire cavity barriers – 65% complete
- Installation of render carrier board – 20% complete
Next steps planned for May:
- Completion of vertical railing installation
- Continue to install new insulation
- Continue to install new fire cavity barriers
- Commence boarding
Large Block (Social rented homes)
Current progress this month:
- Installation of new cladding support system – 95% complete
- Installation of vertical railing – 40% complete
- Installation of new insulation – 20% complete
- Installation of new fire cavity barriers – 30% complete
- Installation of render carrier board – 20% complete
- Existing steel areas have been cleaned and coated
Next steps planned for May:
- Completion of vertical railing installation
- Continue to install new insulation
- Continue to install new fire cavity barriers
Commence boarding
March 2026
Work is fully underway again at Riverside Place, with our contractor making good progress. We aim to share updates with you each month from the contractor breaking down the different tasks being worked on, and how far we have progressed with them.
This is similar to the way we have shared updates with you in the past and will ensure you can see the regular progress being made, rather than just completed milestones.
Small Block (Shared Ownership homes)
Current progress this month:
- Installation of sheathing board and membrane – 100% completed
- Intumescent coatings to steelwork in car park area – 40%
- Installation of the new cladding support system – 30%
- Installation of the new fire cavity barriers – 25%
- Installation of new insulation – 25%
Next steps planned for April:
- Completion of intumescent coatings to steelwork in car park
- Continuation of the new cladding support system
- Continuation of the new fire cavity barriers and insulation
- Commencement of render carrier board
Large Block (Social rented homes)
Current progress this month:
- Installation of sheathing board and membrane – 100% completed
- Intumescent coatings to steelworks in car park area – 30%
- Installation of the new cladding support system – 20%
- Installation of the new fire cavity barriers – 15%
- Installation of new insulation – 5%
Next steps planned for April:
- Completion of intumescent coatings to steelwork in car park
- Continuation of the new cladding support system
- Continuation of the new fire cavity barriers and insulation
- Commencement of render carrier board
February 2026
We mentioned last month our contractor was securing subcontractors for the work. This process is now complete.
Our contractor has submitted all documentation required for Building Control to review.
On site, work has now progressed on the cladding support rail. This is to the south elevations on both blocks and once completed it will allow access to repair the water supply to the building.
January 2026
We have been granted the necessary planning permission amendment required for the change of material to the external facade.
This approval allows our contractors to get working on installing the new framing system and render.
Our contractor is currently securing subcontractors and are due to commence works in February 2026.